Implementation Guide Summary

Introduction

This is MazeMap Implementation Guide gives an overview of the steps for the delivery of MazeMap Maps.

A dedicated Customer Success Manager will be in charge of the delivery phase and will be the key point of contact.

Table of Contents
minLevel1
maxLevel2
outlinefalse
stylenone
typelist
printabletrue

Typical Project Deliverables

...

Deliverable

Responsible to Deliver

Project Kick Off Meeting

MazeMap / Customer

Access to the Admin Tool

MazeMapĀ 

Training Plan

MazeMap

Access to Support and Documentation

MazeMap

Provide Building Manifest, POI list (room data) and CAD files.

Customer

Provide training sessions (POI + path tool)

MazeMap

Tweak/add manual POI data

Customer (MazeMap will provide training)

Integrations

Customer / MazeMap

Delivered Maps and Routing *

MazeMap

Tweak map views

Customer

Map Integrations and embedding

Customer

...

The kick off Phase signals the beginning of your MazeMap project delivery. It involves a collaborative meeting to establish tasks, deliverables, and deadlines for a successful engagement.

During this phase, the Customer Success Manager and the Customer will arrange regular project status meetings, with the frequency and reporting methods tailored to the project's scale and your preferences.

As part of this phase, MazeMap will work with the customer to define a tailored training plan for administrators, IT staff, and key operational users. This ensures that the team is fully prepared to manage the platform before deployment. The training will align with the organisation's needs and follow the overall project timeline. For a detailed breakdown of training phases and user roles, refer to the MazeMap Training Plan.

Duration and Timeline:

Estimated duration: This varies on the size of the area to be mapped for the customer, scope of integrations. A launch date will be agreed during the kick off Meeting.

...

  • Kick off meeting with the MazeMap team

  • Customer setup and granted access to the MazeMap Admin Tool

  • Customer access to user and JS API documentation (if applicable)

  • Customer handing over campus, building and POI data.

  • Training Plan Developed

  • Review provided floor plan drawings

  • Initial mapping of one building to verify drawing quality and POI list

...